Serious question, how do you handle a pour when the ready mix truck shows up 90 minutes late?
Had a slab pour out in Garland last month where the truck sat in traffic for an hour and a half and by the time it got to us that mix was already starting to stiffen up. We had two guys on the chute and the stuff was coming out in clumps, so we ended up adding water at the job site just to get it workable and I know that's a bad habit. The slab cured fine but I keep thinking about what else we could've done besides panicking and watering it down. What do you all do when the truck is way behind, do you reject it or try to work with what shows up? Would like to hear how the old hands on here handle it.